FORWARD TOGETHER

 

Construction Timeline

The following is the estimated construction timeline for the new arena and parking garage. 

Estimated Date   Project Detail
November 2013   Bid the parking garage for Construction
December 2013   Begin construction on Parking Garage
May 2014   Bid construction of hill drive and new arena
June 2014   Begin construction of new arena
August 2014   Parking Garage is completed and opens for use
January 1, 2016   New Arena Opens

Construction timeline for the north endzone and Vaught-Hemwingway Stadium expansion is still being finalized. Check back for more information in the coming months.

Aerial Concept- Ole Miss Entertainment and Sports Arena - (Click to Enlarge)

Arena